DCS SYSTEM - BINH DUONG WASTE POWER PLANT (BIWASE)

DCS SYSTEM - BINH DUONG WASTE POWER PLANT (BIWASE)

Project Name: Dcs System - Binh Duong Waste Power Plant (Biwase)
Investor: BIWASE
Location: Binh Duong
Industry: Water & Wastewater
Implementation Time: 2022-2023

Technical assistance

DCS SYSTEM - BINH DUONG WASTE POWER PLANT (BIWASE)

Scope & Solutions:

  • Control intermediate measuring devices in the operation line that are connected to the DCS system.
  • Monitor the main operating parameters of the Siemens power generation turbine system.
  • Monitor the main operating parameters of related systems such as the boiler system and the waste incineration system.
  • Monitor power meters and AVR switchboards.
  • The DCS system’s operator computer interfaces display the operating status parameters of related systems and provide supervision of the entire plant operation line.

Customer benefits:

  • The system recovers heat from waste incineration to generate electricity for plant operations.
  • The system applies Siemens solutions and equipment such as the TCS T3000 control system, turbine, and other field devices.
  • ESTEC provides the DCS system using S7-400 combined with ET-200SP HA on the latest PCS7 V9.1 platform, designed to Siemens’ leading standards in the DCS field